Objective of the project
The renovation and modernisation of the Zhytomyr hospital unit that provides rehabilitation services for wounded soldiers.
Project activities and status:
- Preparing a technical project for the reconstruction of the building.
- Reconstructing the building of the Zhytomyr Rehabilitation Centre.
- Equipping the Zhytomyr Rehabilitation Centre with the necessary equipment.
The technical design service contract was signed on May 28, 2025. The technical project was prepared on December 21, 2025 and received a positive expert assessment.
On February 6, 2026, a tender for construction work was announced. On April 24, 2026, a contract for the construction was signed.
In addition, medical and rehabilitation equipment is being procured to equip the facility. Public procurement procedures for these purchases were launched in September 2026.